Guodian Beilun power plant became the largest plant
Jun 10, 2009 | en.sxcoal.com

Along with the completion of the third phase of the construction of Guodian Beilun power plant on Jun 2, the power plant became China's biggest thermal power plant with an installed capacity of 5 million kilowatts, as a seventh power unit came online.

As its plan, two 1000MW super-critical coal-fired generator sets has be installed in its third stage of construction, as well as the facilities of flue gas desulfurization and denitrification.

The designed annual power generation of this Zhejiang-based plant is 27.5 billion kWh.

The company has five 600-megawatt units and two million-kilowatt units in operation.

Up to May of 2008, the Beilun power Plant has generated 222.56 billion kWh since the very day of its founding.
 

  E-mail   Save   Print
Prev : Power consumption dip 2.58% in May but decrease slows
Next : Power generators sign contracts with GZ and XJ miners
Relevant News:
Huaneng Power Q1 output up 4 pct on yr Apr 16, 2014
China Shenhua to raise investment in power plants Apr 8, 2014
China Feb power use down 13 pct on mth Mar 21, 2014
China’s power sector reform on the way Mar 21, 2014
China Resources Power 2013 net profit surges 47.3 pct Mar 18, 2014
RECOMMEND THIS STORY
Recommend It: Average (75 votes)

Phone:0086-351-7219322 Fax:0086-351-4728543 
Copyright © 2009-2012 Shanxi Fenwei Energy Consulting Co.,Ltd.All rights reserved.